If you are going to appear for PMP Certification Exam, check out the latest updates about PMP Exam dates. This is part-3 in series of PMP Practice Exam Questions related to Project Schedule Management for PMP Certification covering Project Schedule Management related questions. In the previous part, we discussed PMP Exam questions related to Project Scope Management.
Check out the other PMP Practice Exam Questions part series below:
Here is the list of PMP Practice Exam Questions related to Project Schedule Management.
The Create WBS process identifies the deliverables at the ————— level in the Work Breakdown Structure (WBS)
Choose the correct option?
Correct Answer: A
Check out the solution:
The Create WBS process identifies the deliverables at the lowest level in the WBS, the work package. Project work packages are typically decomposed into smaller components called activities, which represent the work that is necessary to complete the work package.
If you want to compress a project schedule, what are two of the recommended alternatives to consider?
Correct Answer: B
Check out the solution:
Crashing and fast-tracking can compress the project’s schedule when necessary but might come at a higher cost and rework potential.
At the end of a project, what will your schedule variance be equal to?
Correct Answer: A
Check out the solution:
The schedule variance is the earned value minus the planned value. At the end of the project, all of the planned values should be earned, and the difference should be zero.
A technical team can begin to edit a large document 15 days after it begins writing it. What kind of dependency would this represent?
Correct Answer: C
Check out the solution:
The relationship between the two tasks would be represented as a start-to-start with a lag of 15 days. A lag directs a delay in the successor activity.
In a project, Activity A has a duration of four days and begins on the morning of Monday the fourth. The successor Activity, B, has a Finish-to-Start (FS) relationship with A. The Finish-to-Start relationship has two days of lag, and Activity B has a duration of three days. If Saturday and Sunday are non-working days, which of the following statements is true?
Correct Answer: B
Check out the solution:
Activity A has a duration of 4 days and completes by end of the day on Thursday, 7th. There is a 2-day lag, and since Saturday and Sunday are non-working, Activity B can begin only on Tuesday, 12th. Activity B has a duration of 3 days and completes by end of the day on Thursday, 14th.
Which of the following statements regarding Resource Leveling and Resource Smoothing is correct:
Correct Answer: D
Check out the solution:
Resource Leveling can cause the projects’ critical path to change, while Resource Smoothing doesn’t alter the project’s critical path.
Sara is managing a website development project in an agile environment. She wants to create a burndown chart to present the project’s progress to the stakeholders. She adds a diagonal line representing the ideal burndown and a line for daily actual remaining work. She now needs to show the likely variance at the iteration completion. What should she do?
Correct Answer: C
Check out the solution:
A trend line should be added to the daily actual remaining work to forecast the completion.
Predicting future performance based on historical events is called…..?
Correct Answer: B
Check out the solution:
The schedule variance is the earned value minus the planned value. At the end of the project, all of the planned values should be earned, and the difference should be zero.
Which of the following is not an example of parametric estimating?
Correct Answer: D
Check out the solution:
Estimated activity duration based on the actual duration of a previous similar project is an instance of analogous estimating. The other three choices are examples of parametric estimating.
In a small office construction project, the following activities are scheduled in sequence.
What is the minimum time to complete the project if all activities are on a critical path except activity viii, and activity iii is delayed by one day?
Correct Answer: C
Check out the solution:
A critical path has a zero total float. This means that any delay in the critical path activity delays the project finish date. In other words, the critical path gives the minimum time required to complete a project. In this case, adding the durations for all critical path activities gives the minimum time required as 33 days. If activity iii is delayed by one day, then the minimum time required to complete the project will also be delayed by one day, so the minimum time becomes 34 days.
You can find more PMP Practice Exam Project Schedule Management related questions for the PMP Certification here.
Stay in touch as we will be covering all other subject areas of PMP Exam.
Related Articles:
It’s a tough reality: every year, over 14.1 million workers suffer from work-related injuries. For…
If you’ve ever wanted to learn how to cook, but didn’t know where to start,…
Choosing the right career path can be a daunting task, especially with the myriad of…
Believe it or not, the concept of human resources has existed for more than 100…
Web3 managed to change the gaming industry by leveraging blockchain technology. It offers a decentralized…
College is often fun and is filled with lots of activities, especially in the first…