Appearing for PMP Certificate Exam? Get the latest updates about PMP Exam changes here. This is part-5 in series of PMP Practice Exam Questions related to Project Quality Management for PMP Certification covering Project Quality Management related questions. In the previous part, we have discussed about PMP Exam questions related to Project Cost Management.
Check out the other PMP Practice Exam Questions part series below:
Enhance your professional capabilities by enrolling in these Free Quality Management Courses with Certificates.
Which of the following tools and techniques is useful to process work performance data to identify sources of project defects during the Control Quality Process?
Correct Answer: A
Check out the solution:
The question is asking for a tool and technique used during the Control Quality process. Data Analysis is a tool and technique of the Control Quality process used to identify source of defects.
An effective quality audit should be:
Correct Answer: A
Check out the solution:
To provide the best results, a quality audit should be a structured process performed by an independent entity.
A control chart should always contain:
Correct Answer: C
Check out the solution:
Upper and lower control limits allow the control chart to serve its purpose of indicating when a process is in or out of control.
Ready to put your Project Schedule Management expertise to the test? Take a look at our collection of Practice Exams tailored specifically for PMP candidates.
The Plan-Do-Check-Act (PDCA) cycle as the basis for quality improvement is usually attributed to:
Correct Answer: A
Check out the solution:
The plan-do-check-act (PDCA) cycle was defined by Shewhart and later modified by Deming.
Which of the following Manage Quality techniques examines problems, constraints, and non-value-added activities that occur during project work?
Correct Answer: D
Check out the solution:
Process Analysis examines problems, constraints, and non-value- added activities that occur during project work.
The term ———— indicates the degree to which a particular product or service meets requirements, while ————— indicates a category or rank used to distinguish that from other similar items.
Correct Answer: A
Check out the solution:
Grade is a category or rank used to distinguish items that have the same functional use; Quality indicates the degree to which items have meet requirements.
A Planning technique used to provide products, services, and results that truly reflect customer requirements, by translating those customer requirements into the appropriate technical requirements for each phase of project product development, is:
Correct Answer: C
Check out the solution:
The correct response is Voice of the Customer. This is one of the non-proprietary approaches to quality management. In this planning technique, the customer’s requirements are exactly met in the finished product during each phase of the project.
Which of the following processes will determine the correctness of deliverables?
Correct Answer: C
Check out the solution:
An important goal of quality control is to determine the correctness of deliverables. The results of the execution of quality control processes are verified deliverables. These then input to the Validate Scope process for formalized acceptance.
Sheila is the project manager of a website development project. After a detailed discussion with the project management team, she decides to create an informal, broadly framed Project quality management plan. What would your comment on this be?
Correct Answer: C
Check out the solution:
The quality management plan may be formal or informal, highly detailed or broadly framed. Its style and detail are determined by the requirements of the project as defined by the project management team.
Control charts are used to determine the stability of a process. Which of the following best describes the range of the control limits applied on a control chart?
Correct Answer: B
Check out the solution:
The control limits are determined using statistical calculations.
You can find more PMP Practice Exam Questions – Project Quality Management for the PMP Certification here.
Stay in touch as we will be covering all other subject areas of PMP Exam.
Related Articles:
It’s a tough reality: every year, over 14.1 million workers suffer from work-related injuries. For…
If you’ve ever wanted to learn how to cook, but didn’t know where to start,…
Choosing the right career path can be a daunting task, especially with the myriad of…
Believe it or not, the concept of human resources has existed for more than 100…
Web3 managed to change the gaming industry by leveraging blockchain technology. It offers a decentralized…
College is often fun and is filled with lots of activities, especially in the first…